- Client: On Giblin Pty Ltd
- Value: Stage 1 $1.5M and Stage 2 $1.4M
- Construction Period: Stage 1 June 2015 to March 2016 and Stage 2 February 2016 to Current
- Location: Giblin Street, New Town
- Scope of Works: 54 Lots in the first 2 stages including earthworks, underground services, roadworks incorporating urban sensitive stormwater treatment, public reserve and streetscape works
- Superintendents Representative: Johnstone McGee & Gandy Pty Ltd (Chris Males)
- Project Manager: Paul Curry
- Works Supervisor: Marc Duggan
- Project Foreman: Marko Samoukovic and Nigel Crane