- Client: One Care
- Value: $775,000.00
- Construction Period: November 2014 to February 2015
- Location: Barossa Park Aged Care Facility Glenorchy
- Scope of Works: 120m extension of existing twin DN1500 RCP’s and the installation of a third DN2100 RCP in parallel using straight and splay pipes. Associated works included an upstream inlet chamber, gabion outfall headwall, energy dissipation pond and weir.
- Superintendents Representative: BPSM Architects (Damian Rogers)
- Project Manager: Peter Campbell
- Works Supervisor: Marc Duggan
- Project Foreman: Nigel Crane
- *Award: 2015 Tasmanian Branch Winner of the CCF Earth Awards for Excellence in Civil Construction - Category One (Project value up to $1m)